Sunday, May 20, 2007

The Construction Schedule of Everberg Houses

What is the expected construction and completion date of each house here in Everberg Belgium - this the date when the house is turned over to the owner and they can start to live there. At that stage, maybe not everything is finished, such as drive and garden. Sometimes even the interior is not completely finished, however should be good enough to live in.

Here is my estimate based on the progress that we see today - and also based the amount of people working on the site of the different companies (including the hours that the companies are prepared to work each day) and allowance for the weather. The current contractors on site are the Unibuilder and two sub-contractors of the company BIK Maison Woningen.

House 1 -> March 08 ................Unibuilder
House 2 -> December 07.......... Unibuilder
House 3 -> July 08........ ........... BIK -Maison - Woningen
House 4 -> April 08 .................. BIK - Maison - Woningen
House 5 -> July 08 .................... BIK - Maison - Woningen
House 6 -> July 08 .....................BIK - Maison - Woningen
House 7 -> December 07 ...........BIK - Maison - Woningen
House 8 -> May 08 ,,,,,,,,,,,,,.,,,,,,,BIK - Maison - Woningen
House 9 -> ?

How accurate do you think these estimates are ?