We are now in the middle of 2007.
This was apparently when you would have expected all the houses to be finished.
However lets look at the progress of the BIK Maison Woningen projects in Everberg.
So 3 houses that have some progress above ground in the pictures. Only house 7 has significant progress, roof completed, and most of the windows placed - and starting the plastering inside. However they have not done the outside brick pointing. I wonder on the colour?
House 4 - onto the 2nd level for the bricks - but slowed a bit as they are working on the foundations for House 3
House 8 - well this is the longest in progress, since the foundations were there so early. Now making some progress on the brick work.