So what is the progress this week.
House 1 Foundation done
House 2 Roof Completed, mortar in bricks Completed.. looking great
House 3 Foundation started
House 4 Bricks upto first level and first level roof in.
House 5 Not Started
House 6 Not Started
House 7 Bricks completed, and roof battens installed, no tiles yet.
House 8 Bricks started, approx 0.5 to 1 metre
House 9 Cellar started, first base concrete poured